Natural Grass replacement Ricoh Arena

clips

This timelapse shows the work done in december 2014 when GreenFields UK replaced the existing surface, using natural turf, farmed in the Netherlands.  The project at the Ricoh Arena involved site preparation works to remove the existing 8510m2 playing surface before GreenFields UK installed the new natural turf. Works started on 5th December and was completed 6 days in advance of the back to back games and wasps first ever home game at the Ricoh on the weekend of 20th December.